Digital modernisation pricing-readiness gate

Use before approving a delivery estimate or request for quote. It tests whether scope, architecture, quantities, acceptance and residual risk are controlled enough for the proposed price mechanism.

● CONTROLLEDOWNER / SYSTEM 8REVIEW / MONTHLY
01

Authority and zero gate

  • Name outcome, service, information, architecture, security, records, operations, procurement, finance and acceptance owners.
  • Preserve request, clarifications, discovery evidence, estimate versions and approvals.
  • Do not treat a preferred product, budget ceiling or deadline as a verified requirement.
  • Do not release a fixed delivery price when material scope or output specifications remain unknown.
  • Permit a fixed-price discovery only when its own inputs, timebox, deliverables and acceptance are controlled.
02

Minimum controlled artifact set

ARTIFACTMINIMUM CONTENTOWNER
Outcome briefProblem, users, policy/value, measures, constraintsService owner
Current-state inventoryInformation, apps, workflows, integrations, identities, volumesTechnical/information owners
Requirements baselinePrioritised functional and quality requirements with sourcesProduct/acceptance owner
Options recordViable architectures, trade-offs, rejection reasonsArchitecture owner
Delivery modelWork packages, dependencies, responsibilities, scheduleDelivery owner
Acceptance modelMeasures, tolerances, personas, evidence, signatoriesAcceptance owner
Estimate basisQuantities, effort, rates, ranges, contingency, confidenceEstimator/commercial owner
03

Unknowns and assumptions register

IDPLANESTATEMENTEVIDENCE/TREATMENTOWNER/DATE
U-001MigrationLegacy form count and remediation classSMAT + representative inspectionMigration owner / gate date
U-002IdentityExternal-user population and assuranceDirectory sample + identity spikeSecurity owner / gate date
U-003IntegrationNightly export is authoritativeTrace producer, consumer and exception pathData owner / gate date

Classify each as observed, assumed or unresolved. Resolve, prototype, bound, allocate or exclude; never silently convert an unknown into fixed scope.

04

Outcome, scope and requirements gate

  • Outcome and measurable value are named independently of platform.
  • In-scope and out-of-scope users, journeys, information, locations and lifecycle states are explicit.
  • Functional requirements include exception, correction and administrative paths.
  • Quality requirements cover accessibility, security, privacy, reliability, performance, compatibility, maintainability and portability as applicable.
  • Priorities, requirement sources, conflicts and approval authority are recorded.
  • A change-control baseline exists without preventing iterative refinement inside agreed tolerances.
05

Architecture and dependency gate

BOUNDARYREQUIRED PROOFBLOCKER
Platform fitOptions compared against requirementsProduct selected only by preference
InformationSources, ownership, quality, retention, dispositionUnknown authoritative record
Identity/securityPersonas, trust boundaries, isolation testsUnproved external access model
IntegrationInterface, volume, failure and ownership evidenceUninspected critical dependency
MigrationInventory, transformation, reconciliation, coexistenceStorage total used as full scope
OperationsSupport, monitoring, recovery, release, exitNo accountable operator
06

Acceptance and responsibility gate

  • Each deliverable has objective acceptance evidence, tolerance, reviewer and decision time.
  • Critical user journeys include positive, negative, exception and accessibility tests.
  • Migration acceptance distinguishes reconciliation, integrity, permissions, search and business usability.
  • Buyer, supplier and third-party inputs are assigned with dates and consequences.
  • Licensing, environments, data access, test participants and authoritative decisions have named providers.
  • Warranty, defect, change and new-scope definitions do not overlap ambiguously.
07

Estimate construction and confidence gate

WORK PACKAGEQUANTITY/BASISLOW / LIKELY / HIGHCONFIDENCEDRIVER
Representative migration unitScanned objects by remediation classEffort rangeHigh/medium/lowData quality, versions, permissions
  • Include analysis, quality, release, operations transition and management as separate effort rows alongside build effort.
  • Separate labour, licenses, consumption, expenses, buyer effort and third-party charges.
  • State currency, GST, rates, escalation, validity, schedule and capacity assumptions.
  • Explain contingency causally and calibrate with completed comparable work where available.
  • Version the estimate and retain variance evidence at the same work-breakdown level.
08

Price-mechanism decision

CONDITIONCANDIDATE MECHANISMCONTROL
Defined repeatable outputFixed priceFixed scope, quality, acceptance and change rules
Bounded learning objectiveFixed-price discovery/spikeTimebox, questions, evidence deliverables, stop decision
Material unresolved complexityCapped time and materialsBurn visibility, ceiling, stop/replan points
Shared cost uncertaintyTarget cost/incentiveOpen-book basis and gain/pain rules
Progressive confidenceStage or option contractIndependent gates and no automatic full-build commitment
09

Gate decision, evidence pack and cadence

Record PASS, CONDITIONAL or FAIL for each gate, the evidence URI, reviewer, date and expiry trigger. Overall outcomes are: release the proposed price mechanism; narrow/split scope; commission discovery or proof; change commercial model; defer; or stop.

Retain inventories and scans, workshop evidence, requirements, quality model, options, spikes, risks, assumptions, work breakdown, estimate calculations, responsibilities, acceptance, commercial rationale and approvals.

  • At request release: confirm comparable and accessible bidder information.
  • Before contract: rerun all gates against final clarifications and terms.
  • At each stage: rebaseline only through controlled evidence.
  • After completion: compare estimate and actual by work package and update reference classes.

Passing establishes decision readiness. Cost, schedule and platform remain conditional on the recorded assumptions. Procurement rules and legal advice must be applied for the buyer's actual jurisdiction.